WATT.ma Technical Resource Guide

Installer Commissioning Checklist

A concise field reference checklist for electrical contractors installing chargers in Morocco.

View guide ↓
Coming Soon

What you'll learn

01

Pre-power check: voltage measurements, phase rotation, ground resistance (< 10 ohms)

02

Power-on test: LED indicator status and internal breaker verification

03

Network test: SIM card signal RSSI and WebSocket connection ping

04

Final handoff: customer sign-off sheet and portal activation link

Who this is for

Field ElectriciansSite InspectorsCommissioning EngineersProject Managers

Technical Overview & Specification

Use this quick reference field checklist before leaving the installation site to guarantee 100% operational success and instant network connectivity.

1. Phase 1: Physical & Electrical Verification

Verify ground loop resistance is below 10 Ohms. Confirm 400V line-to-line and 230V line-to-neutral measurements. Ensure Type B RCD is armed.

2. Phase 2: Firmware & Communication Test

Power up station and confirm green status LED. Verify cellular signal RSSI is stronger than -85 dBm. Confirm WebSocket handshake with WATT.ma.

3. Phase 3: Live Session Test & Handoff

Tap test RFID card, plug vehicle or simulator, and confirm charging current initiates within 5 seconds. Send sign-off photos to [email protected].

Consult WATT.ma technical guides on electric vehicle charging.